Current Projects

Construction Projects Around the City banner

Current Projects

 Following is  information on current construction projects around the city, including  city projects as well as private construction projects.  Storm Water Pollution Prevention Plan (SWPPP):  any construction site / land disturbance over an acre of property is required to have a SWPPP in place and will be monitored by the city's storm water manager for compliance.  For questions or concerns please contact, Daniel Schuler - Clearfield City Public Works Inspector/Storm Water Manager/Fleet Superintendent at 801-525-4404 (office), 801-940-2078 (cell), or email.  

Last updated: March 15th, 2017 

                             Project   / Contractor Address / Location

Under Construction artwork
Park Village, 
Ivory Homes.  (SWPPP) / 1000 West 300 North
Status:  2 lots remaining; Six lots are currently under construction.

Under Construction artwork
University Ridge Subdivision, 
Mark Koehler. (SWPPP) / 2000 East 926 South
Status: Building town homes.  Asphalt installed Contractor will continue
 to install  driveways and repair some sections of curb that are damaged,
                             also work on areas that need landscaping. Construction on commercial
                             building located north corner of 2000 East 926 South intersection.
                                  
Under construction artwork 
Tanner Clinic parking lot, Legendary X. (SWPPP)  / Robins Drive (1500 East)
Status: Parking lot is completed, contractor will be working on landscaping
 in the planter boxes and park strip this spring.   
under construction artwork
West Square, Ironwood. (SWPPP)     / 700 South, S.R. 193 & Depot St.
Status:  All utilities are installed to city standards.(No construction work at
 this time). 
under construction artwork
Bravo Academy, 
Castle Creek Homes. (SWPPP) / Antelope Drive/575 East
Status: Dirt hauled away, leveling area (No construction work at this time).  

under construction artwork
 Let Them Be Kids,  
Elk Valley Const. (SWPPP) / 1600 South 823 West
 Status:  New daycare building is under Construction, contractor is
 cleaning up site.  
under construction artwork
City Centre Apartments, 
Highmark Const.  (SWPPP) /50 South State St.
Status:  Cleaning up site, hauling away dirt;  installing footings
  and foundations for underground parking area, continuing construction on the
                              apartments. 
under construction artwork
Jon's Park, 
Wall Bros. Const.  (SWPPP) / Pacific Street, 125-160 North
Status: Completed walk through; contractor has punch list to go through and fix listed items, sidewalk, curb and gutters, and landscaping.
under construction artwork
350 West (City project), 
Kapp Const.  / 350 West 2300 to 2150 South
Status: Contractor almost completed with work, will finish up with the  
park strip landscaping in the spring time.                     
construction
Dollar Tree, Leading Tech Const. (SWPPP) /  575 North  Main St.          
Status:  Utilities being installed, construction on building is near
completion   
                  
construction
Wilcox Farms Phase 5,
Josh Staheli Excavating/ 823, 848 West 1600 South
Status:
 project near completion, contractor will work on cleanup, lighting,
 and landscaping in the park strip.                                    
  construction site sign   
Americold addition, Americold (SWPPP)/ 1755 East 1700 South
Status: Construction on new road along west end of project and footings 
for new building.  

construction sign
650 North I-15 Interchange/Intersection Improvement Project,
UDOT (SWPPP) / 650 North & I-15 Interchange. 
Status: Construction on 650 North, under the overpass (I-15).
                             for questions or concerns please contact Bill Crowley, Project Manager for COP  
                             construction  (801-597-4839). 
                            
                           
construction artwork

Contact Info

Public Works

497 South Main
Clearfield, UT 84015
801-525-4404
Hours: 8 a.m.-5 p.m.